Park Talk June 2025
Lake Skinner Projects: Sewer/Water (PK-ARPA003), Repaving Project (PK-ARPA004), and Boat Launch Repair (PK-ARPA011) • Budget: $8.3 million • Status: Under Construction • Completion Date: August 2025 PK-ARPA005: Rancho Jurupa Park Repaving Project
• Budget: $3 million • Status: Complete PK-ARPA006: OHV Feasibility Study: Phase II • Budget: $527K • Status: In progress • Completion Date: February 2026 PK-ARPA007: Tourism Recovery Program
• Budget: $417, 468 • Status: In progress • Completion Date: December 2025 PK-ARPA008: District IV Park Feasibility Study • Budget: $443K • Status: In progress • Completion Date: July 2026 PK-ARPA009: Santa Ana River Bottom (SARB) Maintenance Building • Budget: $6.2 million • Status: Under Construction • Completion Date: February 2026 PK-ARPA010: Santa Ana River Wayfinding Signage Program • Budget: $1million • Status: Under Construction • Completion Date: Summer 2025 PK-ARPA012 Santa Rosa Plateau Broadband
• Budget: $100,000 • Status: Complete PK-ARPA013: Lawler Lodge ADA Improvements • Budget: $3.2 million • Status: Under Construction • Completion Date: December 2025 PK-ARPA014: Kabian Park Improvements • Budget: $2 million
• Status: Under Construction • Completion Date: Fall 2025 PK-ARPA015: Lake Cahuilla Paving, Master Plan & Amenity Upgrade • Budget: $10.9 million
• Status: Paving is complete, amenity update is under construction and Master Plan is in progress. • Completion Date: Amenity Update will be complete August 2025, and Master Plan will be completed Winter 2026. PK-ARPA016: Hidden Valley Nature Center Improvements • Budget: $4.2 million • Status: Under Construction • Completion Date: October 2025 PK-ARPA017: Hurkey Creek Park Beautification • Budget: $1 million
• Status: Under Construction • Completion Date: July 2025 ARPA Projects Progress Report 7